The Door glass was replaced on the presses and the reinstalled on Mp#1. The ANSI compliance gates under Mp#0 and #1 were modified with a hinge by Mike Sells.
Andy made up over thirty new waterlines for the molds with quick disconnect fittings and refilled the FRL's in molding and on the mezzanine.
Roy chased out the platen holes on MP#27.
I corrected the phase on Mp#27, for pump and receptacles. I put the conveyor control box together for press #11.
All that remains is mounting the box and tieing the conveyor motor into it.
I am not sure if they got the bolts painted, the hose reels mounted, or any lubrication done to Mp#27 at this time as everyone left at different times around 7.
There is no more plexiglas left, more will need to be ordered.
Have a great day!